| 1887 |
A.E. Waterman was granted authorization, by ordinance, to light the City of Ocala with electricity. |
| 1889 |
City of Ocala repealed 1887 ordinance and granted a franchise to the Ocala Light & Power Company giving it the right to erect and place poles, wires, and operate the plant through the streets, lanes, alleys and avenues of the City of Ocala. |
| 1898 |
City of Ocala purchased the assets of Ocala Light & Power & a new generator and began serving the citizens of Ocala with electricity. |
| 1898 |
J. C. Norcross became Superintendent of Light & Water for City of Ocala. |
| 1910 |
L. Boyd McKinsey became Superintendent of Light & Water for City of Ocala. (500KWD load) |
| 1916 |
City constructed new power plant (size unknown) to serve 600 customers. |
| 1923 |
City placed the power plant on standby and started purchasing power wholesale from the Camp organization who owned a hydro electric plant in Dunnellon. This plant was eventually bought by FPC. |
| 1931 |
City extended distribution lines South on Shady Road, West on US 27 to Blichton and East on SR 40 to Lynne. |
| 1940 |
Lloyd Lutz became Superintendent of Light & Water for City of Ocala. |
| 1952 |
Burt C. Oliver became Superintendent of Light & Water for City of Ocala. |
| 1959 |
Completed construction of North and East (Sharpes Ferry) 69/4 kV Substations and 69 kV transmission lines. |
| 1960 |
Served 10,000 customers and system demand was 19MW. |
| 1964 |
Completed construction of South (Dixie) and West (Shady) 69/4 kV Substations and Maricamp 69 kV Switching Station and 69 kV transmission lines. |
| 1965 |
Tom Carey served as Superintendent of Light & Water for City of Ocala. |
| 1965 |
E.C. Shreve, Jr. became Director of the Light & Water Department for City of Ocala. |
| 1968 |
A new, separate building was constructed which housed the Utilities Business Office & Electric/Water & Sewer Administration. This building also housed Reproduction (now IT) and Purchasing Departments. |
| 1968 |
Hurricane Gladys took down transmission lines south of Ocala. |
| 1969 |
Completed construction of Enzian and Silver Springs 69/12 kV Substations and 69 kV transmission lines. |
| 1970 |
Completed construction of Richmond Heights 69/12 kV Substation tapping to existing 69 kV transmission lines. |
| 1971 |
Completed construction of Clyatt Park and Downtown 69/4 kV Substations tapping to existing 69 kV transmission lines. |
| 1974 |
Completed construction of New Main (Anthony Road) 69/4 kV Substation and 69 kV transmission line. |
| 1974 |
Added 15 MVA power transformer and three 12 kV distribution circuits at Maricamp Substation. |
| 1975 |
E.C. "Charlie" Shreve, Jr. became Director of the Electric Department for City of Ocala when Water & Sewer became a separate department. |
| 1975 |
Upgraded Enzian Substation 10 MVA power transformer to 15 MVA. |
| 1975 |
Upgraded distribution voltages (4 kV to 12 kV) and power transformers (10 MVA to 15 MVA) at Dixie, North, Shady and Sharpes Ferry Substations. |
| 1976 |
Added second 10 MVA power transformer and three 4 kV distribution circuits at Downtown Substation. |
| 1977 |
City of Ocala purchased from Florida Power Corporation a 1.333% interest in the new Crystal River Nuclear Power Plant. |
| 1977 |
Dean G. Shaw became Director of the Electric Department for the City of Ocala. |
| 1977 |
Utilities Business Office, which had been under Finance Department, became a division of the Electric Department. |
| 1978 |
Completed construction of Ocala #1 230/69 kV Substation and 6905, 6935, and 6955 transmission lines, Ocala's first 230 kV substation. |
| 1978 |
Florida Municipal Power Agency was formed in Orlando. Ocala was a founding member. |
| 1979 |
Current Diversion Program was begun within Meter Division to investigate theft of electricity. |
| 1980 |
Completed construction of Dayco #1 and Dayco #2 69/4 kV Substations tapped to existing 69 kV Maricamp Substation bus and 6960 transmission line, respectfully. |
| 1980 |
Added second 10 MVA power transformer and two 12 kV distribution circuits at Silver Springs Substation. |
| 1980 |
26,500 customers, 500gwh and 120MW demand. |
| 1980 |
Decommissioned and dismantled New Main (Anthony Road) 69/4 kV Substation. |
| 1980 |
Energy Management Division was created to comply with a mandate from the Federal Government to provide information and assistance regarding energy usage to all utility customers. |
| 1981 |
Changed color of all large trucks used by the Electric Department from white to safety yellow to provide distinctive identification as well as high visibility in all types of weather. |
| 1982 |
Completed construction of Paddock Mall 69/12 kV Substation integrated into existing 69 kV transmission lines. |
| 1982 |
OEU's Apprentice Program was approved by the State of Florida and the V.A. |
| 1982 |
Installed pilot wire relay between substations using hard wire (copper), as part of the Systems Improvement Project. |
| 1983 |
Took over responsibility for all "White Way Lights" from the City's Traffic Division. In conjunction with this change, a Streetlight Technician and vehicle were transferred from Engineering / Traffic Division to Electric / T&D Division. |
| 1984 |
Municipal Service Complex construction completed which included an Electric building to house 6 Electric Divisions: Administration, Transmission & Distribution, Energy Management, Meter, Substation and Engineering. |
| 1984 |
Installed a SCADA (Supervisory, Control and Data Acquisition) System. |
| 1985 |
Completed construction of Ocala #2 230/69 kV Substation and 6917 and 6920 transmission lines, Ocala's second 230 kV substation. |
| 1985 |
Sent crews to Tallahassee over Thanksgiving due to an ice storm. |
| 1986 |
Upgraded Richmond Heights Substation 10 MVA power transformer to 18 MVA. |
| 1986 |
Ocala ended its contract with Florida Power for purchase of power so it could instead purchase its power through FMPA at a reduced cost. |
| 1986 |
Ocala, along with 4 other municipal electric utilities in Florida, became a founding member of the All-Requirements Project of FMPA. |
| 1987 |
Completed construction of Baseline and Water Plant 69/12 kV Substations tapping to existing 69 kV transmission lines, using motor operated airbrake switches. |
| 1988 |
Employees moved back into the remodeled Utilities Business Office (UBO) building. (3/28/88) |
| 1989 |
Added second 18 MVA power transformer and three 12 kV distribution circuits at Paddock Mall Substation. All engineering and construction was performed by Electric Utility employees. |
| 1990 |
45,700 customers, 869gwh and 205MWD |
| 1990 |
Completed construction of Airport 69/12 kV Substation and 6975 transmission line. |
| 1990 |
Upgraded Downtown Substation from 4 kV to 12 kV. |
| 1990 |
Decommissioned and dismantled Old Main 69/4 kV Substation, Ocala's first substation. |
| 1990 |
Decommissioned Clyatt Park 69/4 kV Substation. |
| 1990 |
Changed Dayco #1 Substation 10 MVA power transformer with a 5 MVA power transformer with Load Tap Changer (LTC). |
| 1991 |
Installed first fiber optic (multi-mode) cable for relaying and SCADA communications between Ocala #1 and Sharps Ferry Substations. |
| 1991 |
OEU employees completed 500,000 hours worked with no lost time accidents for the first time in a Risk Management Safety Awards Program. |
| 1992 |
Programmable Voice Response Systems were installed for three OEU divisions: Utilities Business Office, Transmission & Distribution and Energy Management Services. |
| 1992 |
OEU Emergency Restoration Plan (ERP) Manual was developed by OEU personnel. |
| 1992 |
Added 69 kV terminal at Airport Substation to serve Sumter Electric's Martel Substation. |
| 1992 |
OEU employees completed 500,000 hours worked with no lost time accidents for the second time in a Risk Management Safety Awards Program. |
| 1992 |
OEU sent crews to Homestead during a six-week time period for restoration work after Hurricane Andrew. |
| 1993 |
The March 13th storm was a low-pressure system that spawned tornadoes resulting in severe damage to buildings, equipment and power lines in a number of different areas including the Ocala Airport and Scrambletown. It took OEU crews eight days to complete all of the restoration work. |
| 1993 |
Upgraded Silver Springs Substation 12 kV distribution feeder breakers. |
| 1993 |
Added 69 kV terminal at Shady Substation to serve Airport Substation. |
| 1993 |
The Electric Department for the City of Ocala unveiled a new two-color logo (circle with light bulb in the center and lightning bolts on four outer corners, in colors of royal blue and yellow) and changed the name to Ocala Electric Utility. |
| 1994 |
Upgraded North Substation 12 kV distribution feeder breakers. |
| 1994 |
Upgraded Sharpes Ferry Substation 12 kV distribution feeder breakers. |
| 1995 |
Began analyzing power quality and investigating power quality issues. |
| 1995 |
Ocala Electric Utility was designated as a Tree Line USA Utility for the first time. |
| 1995 |
Completed construction of 14 miles of 230 kV transmission line from Ocala #2 Substation to Red Oak Substation. |
| 1995 |
Completed construction of Red Oak 230/69 kV Substation and 6945, 6965, and 6980 transmission lines, Ocala's third 230 kV substation. |
| 1995 |
Renovation and enlargement of the Electric Building at the Municipal Service Complex was completed. |
| 1995 |
A Management Audit of OEU was completed by R.W. Beck Inc. |
| 1995 |
Electric Utility reduced its rates and implemented a 10% utility tax with the result being revenue neutral to the Electric Utility. These changes were made to safeguard the amount of the fund transfer to the General Fund, to prepare for future annexation, and to prepare for impending deregulation of the electric utility industry. |
| 1995 |
Renamed Ocala #1 Substation as Eugene Dearmin Substation. |
| 1996 |
OEU unveiled a new logo which included the name, Ocala Electric Utility, and 3 horizontal, parallel lines all in royal blue. |
| 1996 |
A Telecommunications Enterprise was created which will function as a division of OEU. |
| 1996 |
Completed 800 MHz Radio System Fiber Optic Project. |
| 1996 |
Completed Fiber Optic Backbone System connecting all substations and System Control Center for relaying, SCADA and phone services. |
| 1996 |
OEU employees completed 500,000 hours worked with no lost time accidents for the third time in a Risk Management Safety Awards Program.. |
| 1997 |
OEU staff members developed the first OEU Strategic Plan. |
| 1997 |
Florida Power Corporation (FPC) purchased a part of the 230 kV portion of Dearmin Substation and the short 230 kV transmission line between Dearmin Substation and FPC's Silver Springs Substation. This added a third 230 kV transmission line between FPC's Silver Springs Substation and Seminole Electric Cooperative's Silver Springs North Switching Substation, which provided more capacity for FPC, a second 230 kV source at the Dearmin Substation, and increased reliability for OEU. |
| 1998 |
OEU hired a marketing firm to assist OEU with marketing, advertising, and public relations issues due to impending deregulation of the electric utility industry. |
| 1998 |
Upgraded Dearmin 230/69 kV Substation with a second 230 kV terminal to Seminole Electric's Silver Springs North Switching Station. |
| 1998 |
Unbundled energy rates to prepare for deregulation.(first in Florida to do so) |
| 1998 |
Sent crews to Key West for restoration after Hurricane George. |
| 1999 |
Unveiled a new, two-color (swirl and print in green & gray) OEU logo with a tag line. The logo was registered as a trademark and the tag line was registered as a service mark. The wording is as follows: Ocala Electric Utility/Connecting the Community/City of Ocala |
| 1999 |
Upgraded Dixie Substation 12 kV distribution feeder breakers. |
| 1999 |
Renamed Ocala #2 Substation as Gerald K. Ergle Substation. |
| 2000 |
Theodore the Electric (Ted E.) Bear was introduced as OEU's new mascot. |
| 2000 |
OEU employees completed 500,000 hours worked with no lost time accidents for the fourth time in a Risk Management Safety Awards Program. |
| 2000 |
Dismantled Clyatt Park Substation steel structures for the use at Red Oak 69/12 kV Substation addition. |
| 2000 |
Added 18 MVA power transformer and four 12 kV distribution circuits to Red Oak 230/69/12 kV Substation. All construction performed by OEU employees. |
| 2000 |
Upgraded Shady Substation 12 kV distribution feeder breakers. |
| 2000 |
45,900 customers, 1,200GWH and 300MWD peak |
| 2001 |
Hurricane Gabrielle resulted in 6,000 customers out of power. |
| 2001 |
Designed, engineered, and wrote specifications for Ocala Palms Substation. |
| 2002 |
A new Customer Service Center building opened in downtown Ocala, to house 3 Electric divisions: Customer Services Office, Energy Management Services, and Telecommunications. |
| 2002 |
Completed construction of Ocala Palms 69/12 kV Substation. All engineering and construction was performed by OEU employees. |
| 2002 |
Upgraded 15 MVA power transformer at both Dixie and North Substations to 25 MVA. |
| 2003 |
Established ongoing Engineering contracts with Jones, Edmunds Associates and R.W. Beck, Inc.to perform engineering services on a project by project basis. ( no retainer fee) |
| 2003 |
Replaced 30-year old mainframe-based utility billing system with new PC-based Customer Information System (CIS). |
| 2003 |
A Management Study of OEU was completed. |
| 2003 |
Leased the former Aircraft Rescue Firefighting Facility (ARFF) from the Airport, for future use as a West Ocala Operations Center for OEU. |
| 2003 |
Ocala Electric Utility was designated as a Tree Line USA Utility for the second time. |
| 2003 |
Upgraded 15 MVA power transformer at Enzian Substation to 25 MVA. |
| 2003 |
OEU completed entry of all circuits into a Geographic Information System (GIS). |
| 2003 |
Replaced old SCADA (Supervisory, Control and Data Acquisition) System with a new SCADA System. |
| 2003 |
Jones, Edmunds & Associates was authorized to study adding 230 kV line from Silver Springs North to improve system reliability |
| 2004 |
Ocala Electric Utility was designated as a Tree Line USA Utility for the third time. |
| 2004 |
Began using the West Ocala Operations Center for an alternate T&D base and for training. |
| 2004 |
Ocala Palms 69/12 kV Substation was brought on line with the new 6930 transmission line extension as part of Ocala Palms Project. |
| 2004 |
A total of 47 Apprentices have graduated from the program since the program's inception. |
| 2004 |
Jones, Edmunds & Associates was authorized to study the route of a 69 kV line to the proposed Nuby's station. |
| 2004 |
Jones, Edmunds & Associates was authorized to develop a revised license agreement with Seminole Electric to add the second 230 kV line between Ergle Substation and Silver Springs North Substation. |
| 2004 |
Dean G. Shaw, Director of OEU, retired after 26+ years of service. He served as Director from July 7, 1977 to April 16, 2004. |
| 2004 |
Renamed Red Oak Substation to Dean G. Shaw Substation. |
| 2004 |
Rebecca "Becky" M. Mattey became Director of OEU on April 19, 2004. |
| 2004 |
Ocala Electric Utility hosted the Florida Lineman's Rodeo Competition in Ocala. |
| 2004 |
OEU sent crews to assist Orlando Utilities Commission and Bartow, under the Mutual Aid Agreement, in the aftermath of Hurricane Charley which hit Florida on September 13. |
| 2004 |
Florida was hit by four hurricanes within a span of six weeks, from September 13 to October 27:Charley, Frances, Ivan and Jeanne. |
| 2004 |
OEU submitted forms to FEMA for disaster recovery assistance for two hurricanes which did a lot of damage to the OEU system: Frances hit on September 3 and Jeanne hit on October 19. |